Project Profile

project2.jpg (4568 bytes)

HRSG SERVICES

Client: Deltak Corporation
Description: HRSG Feedwater Heater Retrofit
Location:
Kalaeloa Cogen Partners, L.P., Kalaeloa,Hawaii
IMAGE33.JPG (8482 bytes)Synopsis: This project was to retrofit feedwater heater panels into the stack inlet duct of two (2) Deltak Heat Recovery Steam Generators. Located on the island of Oahu, Hawaii this presented Bremco, Inc. with a variety of challenges. Bremco, Inc. would be responsible for construction management and supervision coordinating the necessary craft trades, equipment, tooling, subcontracting and materials. Logistical dispatching was coordinated from Bremco, Inc's home office in Claremont, New Hampshire.

The purpose of the feedwater heaters is to increase the temperature of condensate and fresh water makeup flowing through the internal heater by extracting temperature from the flue gas surrounding the exterior tube surfaces of the heater. The water would be increased from 90 degree F to 175 degree F prior to sending it to the deaerator feedwater storage tank. The ultimate gain in temperature will provide an increase in overall thermal efficiency resulting in additional power generation.

Feedwater Heater Tube Panel Installation:

  • Install all required structural steel pedestal supports within the interior breeching space. Extend all pedestal supports through lower duct wall panels and secure to existing structural steel and concrete foundations.
  • Modify all existing internal breeching supports to allow the required spacing for tube panel clearances.
  • Install five (5) new sootblower wall boxes per unit to allow for future sootblowers.
  • Modify the top breeching and provide access for the installation of two (2) tube panels per unit. Install access door assemblies to allow for future inspections and periodic cleaning.
  • Install a tube panel water wash spray system to allow for scheduled water wash cleaning.
  • Install two (2) tube panels per unit weighing approximately 17,000 lbs each.
  • Install upper and lower internal gas baffles to ensure the direction of all flue gases through the tube panel assembly.
  • Fabricate and install 2205 alloy piping between each panel inlet and outlet headers to within 12" outside the exterior HRSG casing.
  • Install pipe casing bellows seals at each casing penetration.

IMAGE34.JPG (11615 bytes)
Photo at top and right showing feedwater panels
being lowerd in HRSG unit

IMAGE35.JPG (14510 bytes)

Condensate Feedwater Piping

  • Fabricate and install all required condensate feedwater piping between the deaerator located at the top of the steam turbine building and each HRSG unit.
  • Fabricate all required pipe support structural assemblies and install along the existing pipe bridge running from the turbine building to each HRSG. Supply and return piping to each HRSG unit totaling 150 to 300 feet respectively.
  • Provide a quality control program consisting of all pipe weld inspection and NDE. Provide hydrostatic testing of all pipe and panel assemblies.
  • Provide all pipe insulation and lagging.

IMAGE36.JPG (16802 bytes)
Pipe bridge with supply and return condensate
piping installed.

IMAGE37.JPG (16706 bytes)